Background

Grouped GEMMs are unlike a vanilla GEMM (a single GEMM problem in a grouped GEMM could be considered a vanilla GEMM).

If M is the value of M-dimension of a GEMM problem (A is sized [M, K], and B is sized [M, N]), and B_M is the block-level tile size's M dimension, then for a single GEMM problem, M-occupancy is computed like this:

Actual number of tiles used = (M + B_M - 1) / B_M
Tiles needed to fit M = M / float(B_M)
M-occupancy = Tiles needed to fit M/Actual number of tiles used

For a single GEMM, if M is large, we typically choose B_M such that M-occupancy is 1, or close to 1, if M is not a multiple of B_M.

For a Grouped GEMM, specifically the one used in MoEs, the M dimension of each expert may vary a lot if load-balancing is not used to route tokens to experts.

As an example, we may end up with M dimension per expert in an MoE layer like,

// 32 experts
  {4, 1026, 1799, 166, 694, 753, 0, 16, 0, 240, 1119, 19, 6, 0, 46, 659, 10, 0, 112, 808, 181, 0, 28, 22, 90, 0, 176, 0, 37, 5, 10, 22},

If we choose the same tiling scheme for all GEMM problems of a grouped GEMM, then with values as divergent as the ones above, we would have low M-occupancy if we choose B_M such as 256, 128, which would result in a significant proportion of compute being wasteful.

However, choosing a smaller B_M would result in lower arithmetic intensity, which may slow down compute.

Question

In your experience, if we use the same tiling scheme to compute all the GEMM problems in a grouped GEMM for MoE (without load-balancing), is the traditional roofline model still helpful in determining what the ideal latency should be? Or do you account for low M occupancy somehow, and adjust the roofline accordingly?

Thank you!

Originally created by @sanchitintel on GitHub (Oct 9, 2025). Original GitHub issue: https://github.com/deepseek-ai/DeepGEMM/issues/211 ### Background Grouped GEMMs are unlike a _vanilla_ GEMM (a single _GEMM problem_ in a grouped GEMM could be considered a _vanilla_ GEMM). If `M` is the value of M-dimension of a GEMM problem (`A` is sized `[M, K]`, and `B` is sized `[M, N]`), and `B_M` is the block-level tile size's M dimension, then for a single GEMM problem, M-occupancy is computed like this: Actual number of tiles used = `(M + B_M - 1) / B_M` Tiles needed to fit `M` = `M / float(B_M)` M-occupancy = `Tiles needed to fit M`/`Actual number of tiles used` For a single GEMM, if `M` is large, we typically choose `B_M` such that M-occupancy is 1, or close to 1, if `M` is not a multiple of `B_M`. For a Grouped GEMM, specifically the one used in MoEs, the `M` dimension of each expert may vary a lot if load-balancing is not used to route tokens to experts. As an example, we may end up with `M` dimension per expert in an MoE layer like, ``` // 32 experts {4, 1026, 1799, 166, 694, 753, 0, 16, 0, 240, 1119, 19, 6, 0, 46, 659, 10, 0, 112, 808, 181, 0, 28, 22, 90, 0, 176, 0, 37, 5, 10, 22}, ``` If we choose the same tiling scheme for all GEMM problems of a grouped GEMM, then with values as divergent as the ones above, we would have low M-occupancy if we choose `B_M` such as `256`, `128`, which would result in a significant proportion of compute being wasteful. However, choosing a smaller `B_M` would result in lower arithmetic intensity, which may slow down compute. ### Question In your experience, if we use the same tiling scheme to compute all the GEMM problems in a grouped GEMM for MoE (without load-balancing), is the traditional roofline model still helpful in determining what the ideal latency should be? Or do you account for low `M occupancy` somehow, and adjust the roofline accordingly? Thank you!
Author
Owner

@sanchitintel commented on GitHub (Oct 9, 2025):

Will choose a more appropriate place to ask this question. Thanks!

<!-- gh-comment-id:3384689064 --> @sanchitintel commented on GitHub (Oct 9, 2025): Will choose a more appropriate place to ask this question. Thanks!
Sign in to join this conversation.
No labels
pull-request
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
deepseek-ai/DeepGEMM#121
No description provided.